Level 10 Weekly
Last meeting: 2026-06-09 — Six Peak Capital - Weekly L10
0
Rocks Complete
0
Actions Closed
0
Open To-Dos
0
Goal Categories
Weekly Summary
2026-06-09 — Six Peak Capital - Weekly L10
- The meeting reviewed development financing status, operator selection, construction contracts, and several administrative actions related to ongoing projects.
- Financing: The preferred-equity investor referred to as LLJ is showing progress and Genesis Capital remains engaged on the debt side; Genesis may also provide mezzanine capital.
- Appraisals are still outstanding and are required to complete underwriting.
- Chris reported that higher rent assumptions improved underwriting but achieving those rents is uncertain; project funding is considered better-than-even versus two months ago.
- The team agreed not to take substantive steps until a signed term sheet; a term-sheet condition requiring a nonprofit and CMFA grant could delay the timeline by roughly six months.
- Operator selection and approvals: Chris summarized the ED1 tenant approval process and risk that Urban Futures (UFBA) can delay approval absent an automatic approval mechanism.
- Tom and Derek described Adaptive’s prior management of an 86-unit comparable deal with ~10-day turnaround when applications are complete.
- The group prioritized an experienced on-site property manager, tasked Tom to request formal proposals from Adaptive and at least two other operators, and set Derek and Chris to prepare the Pitch presentation aimed for summer to allow Pitch diligence and operator selection by roughly January.
- Construction, contracts, and procurement: Hillman construction contract exhibits and outstanding items are expected to be completed this week.
- Schuyler will focus the next six weeks on signing LOIs with three to four GCs/design-build firms and is working with Gores Group to secure materials at cost; Arrow is confirmed as construction architect on one proposal and West of West as design architect.
- The team discussed holding shoring numbers for Scott, excluding a transformer vault and shoring cost from an estimate, and accelerating hiring and producing a draft budget/GMP through Claude as a placeholder if a term sheet arrives.
- Land pricing observation: a purchased lot (3626 Watt Sika in Palms) was listed for sale.
- Regulatory and fundraising: Schuyler reported the TEFRA public hearing is scheduled for Thursday and bond counsel expects no issues; receipt of TEFRA approval plus a mayoral letter and city council motion will permit fundraising to begin.
- Schuyler entered a UCLA City Lab case competition application that could provide favorable construction financing and requested project history and selective financials from Bob to support that application.
- Administration, agreements, and claims: Bob finalized two agreements but several signatures remain, including Justin Kruger’s on the co-invest agreement.
- The bank is withholding a Khalifa job payment because two conditional waivers were submitted instead of one combined waiver; a participant offered to combine the PDFs and resubmit.
- The team reviewed an email seeking the subcontractor responsible for decks/patios and separation details for 2022 and beyond; a participant will call to clarify alleged patio defects before escalating.
- A participant requested a copy of a Copilot camp / 401(k) document.
- Pipeline and other items: Stein declined a proposed pre-development equity role on Borden and lacks deployable cash until Francis closes, leaving guarantees and a potential MRK–Aaron partnership as remaining levers.
- Work is underway to re-form an architecture arrangement with Adam and Tag using Adam's license for Third Street and Reseda.
- No final decisions were made on pending financial close actions.
Action Items
From 2026-06-09
-
Derek Sanders and Chris Aiello Derek Sanders and Chris Aiello will join Genesis’s construction team call regarding the Ramsky utility plan when the lender schedules it.
-
Chris Aiello Chris Aiello will keep the team posted when the Ramsky call is scheduled and pursue approval from the lender.
-
Tom Taggart Tom Taggart will request and collect formal proposals from Adaptive, Jon Stewart, and Wynn and include written answers to the circulated operator questions.
-
Derek Sanders and Chris Aiello Derek Sanders and Chris Aiello will prepare the final presentation and memo for Pitch based on the collected operator proposals.
-
Derek Sanders Derek Sanders will resend the Google Doc with operator questions to Tom so operators provide written responses with their proposals.
-
Bob Kennedy Bob Kennedy will follow up to obtain the remaining signatures on agreements, including reaching out regarding Justin Kruger’s signature.
-
Schuyler Dietz Schuyler Dietz will sign LOIs with three to four GCs/design‑build firms and pursue materials‑at‑cost agreements with the Gores Group over the next month to six weeks.
-
Schuyler Dietz Schuyler Dietz will coordinate with Bob Kennedy to obtain project history and selective financial information needed for the UCLA City Lab case competition application.
-
Chris Aiello Chris Aiello will keep the team posted on financing developments for the blocks
-
Chris Aiello Chris Aiello will work with MRK to pursue partnering with Aaron so the team can act as general contractor on the Borden deal
-
Conference room participant Conference room participant will send the edited combined conditional waiver to the bank and provide a copy to the team.
-
Conference room participant Conference room participant will call the sender to ask what specific defects are being alleged with the patios (slope, sagging, leaking).
-
Conference room participant Conference room participant will send a copy of the Copilot/401(k) document to the requester.
Files Referenced
Needed to keep moving
No files referenced.
To-Dos
Active this week
-
Tom Taggart Venice Lawsuit monitoring from rock2026
-
Derek Sanders Derek Sanders will work with Grady and Greg to finalize loose ends and exhibits on the Hillman construction contract. from action item
-
Bob Kennedy Bob Kennedy will continue to ping co-invest signatories until all required signatures are collected. from action item
Company Rocks
Shared quarterly goals
-
AI WorkflowEstablish the invoice coding AI workflowJuly 31 2026
Individual Rocks
By category, then owner
Finance / Structure / Capital
2 / 3
Chris Andresen & Robert Carrega
2 / 3
-
Review the board portal for accuracy of expensesCMA to keep updating, but eventually we want to add in actuals as time goes byEnd of April
-
Finalize Remaining Restructure ItemsComplete Rich Note and remaining restructure documentsEnd of April
-
Move Investments Out of Six Peak CapitalMove Francis, Ramsgate, Crenshaw, Shadow Way, Reseda to deal-level entitiesEnd of Q3 2026
Asset Management / Transactions
4 / 5
Tom Taggart
2 / 3
-
Choose 2-3 candidates and get proposals/proformas2026-07-01
-
LIHTC Parking StudyConsultant selection and SoCal LIHTC parking analysisEnd of April
-
Reading Lease renewal planRenewal planEnd of April
Chris Aiello
1 / 1
-
Update BBC memo for 4/13 IC meeingPropose Steyn pref equity investment2026-04-13
Chris Aiello & Chris Andresen
1 / 1
-
Finalize 3rd St Closing 4/21Ensure capital calls are out and entities are formed2026-04-21
Development / Construction / Diligence
5 / 7
Chris Aiello
0 / 1
-
Figure out outreach to all tax credit investors that will consider a ground lease structureEnd of Q3 2026
Derek Sanders & Grady Lakamp
0 / 1
-
Francis GMP Contract Finalization & closing budgetNegotiate and finalize GMP with LV / Six Peak / MRK2026-05-15
Derek Sanders (discuss with Grady)
1 / 1
-
Construction photo planFind consistent solution to photo reporting on all construction projectsBy Francis
Derek Sanders & Tom Taggart
1 / 1
-
Reading Utility bill back issuewaiting for a new meter from Weights & Measures to be installed. Need electric to be billed out by QMCASAP
Schuyler Dietz
3 / 3
-
Create a targeted list of outbound dev. site leadsUse database and work with a broker to identify a list of 100+ devt. sites that fit SP parametersEnd of Feb 2026
-
Finalize uplifters memo and term sheetPrepare for May 5 meetings2026-05-05
-
Continue to reach out until the respond2026-03-15
Reporting / Communication / Brand
1 / 1
Schuyler Dietz & Chris Aiello
1 / 1
-
Monthly Reporting to Justin KrugerWeekly notes for Whipple & Califa projects, Monthly construction reports with photosOngoing, starting January
LV Rocks
1 / 2
Schuyler Dietz & Chris Aiello
1 / 1
-
Get Grady comments and finalize websiteEnd of April
Grady Lakamp & Bob Kennedy
0 / 1
-
HR/401k/employees discussionSeptember 15 2026
Governance / Legal / Board
1 / 3
Bob Kennedy
1 / 2
-
MRK Negotiations and finalize MOULead negotiations with MRK and Steyn CapitalBy Francis Closing
-
LIHTC Parking Study OversightOversight of Tom Taggart’s parking studyEnd of Feb 2026
Bob Kennedy & Chris Aiello
0 / 1
-
2859 Francis Debt & Equity ExecutionManage closing logistics/legal with SteynApr–May 2026
Recent Meetings
History
- 2026-06-09 Six Peak Capital - Weekly L10 13 actions
- 2026-06-02 Six Peak Capital - Weekly L10 0 actions
- 2026-05-26 Six Peak Capital - Weekly L10 0 actions
- 2026-05-19 Six Peak Capital - Weekly L10 5 actions
- 2026-04-28 Six Peak Capital - Weekly L10 4 actions
- 2026-04-07 Weekly Six Peak Capital Call 8 actions